Measuring a schedule
Read turnaround, waiting and response times off a Gantt chart, plus throughput and utilisation. About 14 minutes.
A process arrives at 3, first runs at 5 and finishes at 12. Its burst is 4. What is its waiting time?
- A5
- B2
- C9
Show the answer
5. Turnaround is 12 − 3 = 9; take away the 4 units of running and 5 remain.